Public Safety Facility

Case Study

EdgeCool components

Restoring Reliable IT Cooling in a Newly Remodeled Public Safety Facility

As part of a $34 million renovation project, the Frederick Police Department transformed a 67,000-square-foot building into a modern four-story headquarters designed to support public safety operations for years to come.

Reliable network infrastructure is essential in law enforcement environments, supporting communications systems, security infrastructure, records access, and other mission-critical technologies that enable officers and staff to serve the community.

During the original building design, dedicated cooling was specified for the main distribution frame (MDF) room on the 3rd floor using a traditional split system. However, the intermediate distribution frame (IDF) rooms located on the 1st, 2nd, and 4th floors were designed to rely solely on conditioned building air.

Following occupancy, facility operators discovered that the building HVAC system could not adequately manage the heat generated by the IT equipment within the IDF rooms. Temperatures rose during daytime operation, while cooling capacity became even more limited during nights, weekends, and winter months when the building transitioned to heating mode.

A dedicated cooling solution was needed to protect critical network infrastructure and maintain reliable operation throughout the facility.

EdgeCool components

Cooling Demand Exceeded Design Expectations

Although the building had undergone a comprehensive renovation, the heat load generated within the IDF rooms exceeded original engineering assumptions. As network equipment expanded, the existing HVAC system struggled to maintain acceptable temperatures.

Small Telecom Rooms with Limited Space

The IDF rooms are compact environments containing multiple equipment racks, leaving little room for traditional cooling equipment or extensive mechanical modifications.

Cost and Complexity of Mini-Split Installation

Hardesty (installation contractor) evaluated a conventional mini-split air conditioning system as a potential solution. However, installation presented significant challenges, including:

  • Long refrigerant line-set runs
  • Coring through structural floors and exterior building elements
  • Rooftop condenser installation
  • Running electrical power to rooftop equipment
  • Sealing roof penetrations and weatherproofing
  • Coordination among multiple trades

Collectively, these requirements substantially increased project cost and complexity

Maintaining Building Operations

As an active public safety facility, any cooling upgrade needed to minimize disruption while providing long-term reliability for mission-critical infrastructure.

EdgeCool components
EdgeCool components
EdgeCool components

Solution: A Targeted, Flexible Solution with EdgeCool

After evaluating available options, Hardesty selected the EdgeCool In-Rack Cooling System to provide targeted cooling directly at the source of heat generation.

Compared to a traditional mini-split system, EdgeCool delivered an installed solution at half the cost, while avoiding many of the construction challenges associated with conventional air conditioning systems.

Three EdgeCool units were installed in the separate IDF rooms to support the facility’s full telecommunications infrastructure. The systems were integrated into existing telecom two-post racks, maximizing valuable floor space while delivering dedicated cooling precisely where it was needed.

Flexible Installation Options

The project demonstrated EdgeCool’s installation flexibility across different environments:

A

1st and 2nd Floor IDF Rooms

Condenser units were installed directly within available rack space.

A

4th Floor IDF Room

Limited rack capacity led to the condenser unit being installed within the drop ceiling plenum while maintaining effective operation.

A

3 System Install

Installation of all three systems was completed in two days, enabling rapid deployment with minimal facility disruption.

Key Takeaways

Modern public safety facilities depend on reliable IT infrastructure to support communications, security, and day-to-day operations. Even newly renovated buildings can experience unexpected cooling challenges as network demands grow and heat loads evolve.

For the Frederick Police Department project, EdgeCool provided a practical and cost-effective alternative to traditional air conditioning systems—delivering dedicated cooling directly to critical equipment without extensive construction or rooftop modifications.

By avoiding long line-set runs, structural coring, rooftop penetrations, and additional electrical infrastructure, the facility achieved reliable cooling protection while reducing installation cost and complexity.

Most importantly, EdgeCool helped ensure that the technology supporting essential public safety operations remains protected and operational year-round.

EdgeCool brings “best value” in server-cooling for any environment. Get efficiency that pays you back in dollars saved. Let our EdgeCool technical expert spec a system for your environment.

Get a Quote

Product Specifications

UNIT TYPEEvaporator
EVAPORATOR
Condenser
CONDENSER
Model Number (sold separately)A5F5
Electronic ControlProgrammable
Electrical Charateristics
Voltage Requirements (60 Hz)1 Phase, 115 V
Total Power Consumption1.5 kW
NEMA Plug Configuration5-20P
Cooling Capacity and Power Consumption
Evaporator: 95°F @ 32% RH / Condenser: 81°F
Total Cooling Capacity15,400 Btu/h
4.5 kW
Sensible Cooling Capacity13,600 Btu/h
4.0 kW
Power Consumption1.5 kW
Refrigerant
TypeR410-A
Factory Charge Amount1.65 lb
Operating Conditions (Min-Max)65°F @ 50% RH - 113°F @ 30% RH
Max Airflow520/340/210 CFM (high/mid/low)765 CFM (1 speed)
Enclosure Dimensions17 x 33 x 13 in (8U Rack Space)17 x 34 x 16 in (9U Rack Space)
Max. Sound Level68/60/49 dB(A) (high/mid/low)70/72dB(A) (with duct/without duct)
Net Weight57 lb (26 kg)108 lb (49 kg)

Specifications subject to change without notice.

Evaporator Accessories

NO.PART NAMEDESCRIPTIONPART NUMBER
1Evaporator Rack Mount KitRackmounts Evaporator unit inside standard 19-in. Electronics Industries Association (EIA) rack. Includes, stays, brackets and bolts. (Does not include bolts and nuts to connect to vertical mounting rails)484009-1560

Condenser Accessories

NO.PART NAMEDESCRIPTIONPART NUMBER
2Condenser Rack Mount Kit - InternalRackmounts Condenser unit inside standard 19-in. Electronics Industries Association (EIA) rack. Includes, stays, brackets, screws, nuts and bolts. (Does not include bolts and nuts to connect to vertical mounting rails)484009-1580
3Condenser Rack Mount Kit - ExternalRackmounts Condenser unit on top of standard 19-in. Electronics Industries Association (EIA) rack. Includes, stays, brackets, screws, nuts and bolts. (Does not include bolts to connect to rack top panel)484009-1570
4Condenser Mount Rails - External & InternalRackmount adapter rails for deep racks, used with accessory No. 2 or 3484009-1630
5Air Plenum KitPlenum for return air to Condenser. Includes 12-in duct clamp.484009-1590
6Self-Supported Duct12-in diameter white, plastic duct that extends from 6.5 to 10-ft in length. (Includes clamp)LA481744-0410
7Flexible Air Duct12-in diameter wire-reinforced, accordion-style duct in 10-ft length for Condenser air exhaust. (Includes clamp)LAY45771-0060
8Celling Tile, 12-in hole, plastic24-in x 24-in plastic white tile with 12-in hole for exhaust air self-supported duct.LA146373-8280
9Ceiling Tile, 12-in hole, metal24-in x 24-in sheet metal tile with 12-in hole and built-in flange for exhaust air flexible duct kit.484490-1030
10Exhaust DiffuserDiverts exhaust air away from intake air, used for low profile ceilings or industrial areas.
Exhaust diffuser cannot be used for Condenser installation inside the rack.
484009-1610
11Exhaust Flange KitFlange to duct exhaust air away from Condenser. Includes 12-in. duct clamp.484009-1600

Other Accessories

NO.PART NAMEDESCRIPTIONPART NUMBER
12Connection Cable - ExtensionWire Harness A - Power is used when the EdgeCool Condenser unit is installed remotely from rack (> 9 ft. from Evaporator unit). Cable length: 10 ft.481950-4100
13Connection Cable - ExtensionWire Harness B - Signal is used when the EdgeCool Condenser unit is installed remotely from the rack (> 9 ft. from Evaporator unit). Cable length: 10 ft.481950-4110
14InsulationFor server rack insulation/condensation prevention and to improve airflow within the rack.484009-1620
15Pump Adaptor KitAttaches condensate pump (NOT included) to Evaporator unit. Includes bracket and electrical connector.484009-1640